I have set up a resource allocation task in a matrix table (as below). I have four different blocks of a resource (PT sessions) to be allocated to four different people. The drop down boxes simply list the four different blocks of PT sessions (9 sessions, 7 sessions, 5 sessions and 3 sessions) - Is there a way (possibly a validation?) that I can use to ensure that the same block (for example '9 sessions') cannot be allocated to more than one person?
NB. I have tried this with a 'drag and drop' task but unfortunately this doesn't present well when used on phones which most of my participants will be using?
!
Page 1 / 1
@Dannyboy_28 there's a great built in variable for you. When you click on custom validation you should see options for (Count). For these four sessions options you make a rule that all of the (Count) variables are equal to 1.
!
!
Thanks bstrahin - this works perfectly
Leave a Reply
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.